0.4
0.4 Release Plan
This page outlines the goals for the next release of Ubuntu Accomplishments, the 0.4 release. Below you can find the feature goals as well as the content that will be discussed at the forthcoming UDS in Copenhagen.
Feature Goals
TARGET RELEASE: 15th February 2012
Daemon
- No new feature work.
- Complete documentation of the API.
- Bug fixing.
Looking for proper shutdown of twistd process - This is not needed, as we won't need to care about pidfile once the daemons becomes a DBus service.
- Make the daemon a DBus service.
Fix any outstanding Lintian issues (mfisch)
Support for keywords in .accomplishment files. (rafalcieslak256)
- Support for accomplishment's level/diffitulty/time (will be not enabled for community-accomplishments)
Client
- High - Write unit tests.
- High - Ensure the trophies lens works (inc. previews).
- --Medium - Fix PEP-8 issues--
Medium - Explore new designs for a summarized trophy view.
- - Reach out to the community to gather designs. - Finalize the agreed design into an implementation plan.
Medium - Fix any outstanding Lintian issues (mfisch)
- Medium - Implement reacting on daemon's reaload signals
Low - Improve filtering and add a search bar (rafalcieslak256)
- Low - Displaying trophy level/difficulty/time if appropriate.
- Low - Apply wooden cabinet view in the GTK client.
Server
- High - Deploy validation server to Canonical IS (mhall119).
- - Take the validation server codebase and deploy a production service running in the Canonical data center.
- High - Ensure that updates to the validation service can be deployed by us (mhall119).
- High - Deploy web gallery service (mhall119).
- High - Point trophies.ubuntu.com (mhall119).
Accomplishments Collections
https://blueprints.launchpad.net/ubuntu/+spec/community-r-accomplishments-collection-cleanup
- Encouraging contributors to make desktop accomplishments for whatever application they are familiar with.
UDS Plans
Blueprints
Topic |
Owner |
Blueprint |
Webservices |
||
Desktop Clients |
||
Web Gallery |
|
|
Accomplishment Collections |
|
|
Viewer Updates |
|
|
|
|
|
Sessions
Session |
Leader |
Description |
Date/Time |
|
2012-10-31 11:00-11:55 |
||
Preparing Ubuntu Accomplishments client applications for release |
|
2012-10-30 16:15-17:00 |
|
|
|
2012-10-31 17:05-18:00 |
|
|
|
2012-10-31 09:00-09:55 |
|
|
|
2012-10-31 15:00-16:00 |
|
|
|
2012-11-01 12:00-13:00 |
|
|
|
|
|
Accomplishments/0.4 (last edited 2012-11-29 19:06:08 by c-75-71-83-192)