== Schedule ==
Line 12: Line 11:
||<rowbgcolor="#cccccc"> '''Week''' || '''Date''' ~-(Thursday)-~|| '''Task''' || '''Status''' || '''Notes''' || ||<rowbgcolor="#cccccc"> '''Week''' || '''Date''' ~-(Thursday)-~|| '''Work Item Iteration''' || '''Status''' || '''Notes''' ||
Line 14: Line 13:
|| 1 || May 6th || ||<#CCFFCC> || <!> Toolchain Uploaded ||
|| 2 || May 13th || ||<#CCFFCC> || {*} '''Developer Summit''' ||
|| 3 || May 20th || ||<#CCFFCC> || ||
|| 4 || May 27th ||  ||<#CCFFCC> || ||
|| 1 || May 6th || A-2 ||<#CCFFCC> || <!> Toolchain Uploaded ||
|| 2 || May 13th || A-2 ||<#CCFFCC> || {*} '''Developer Summit''' ||
|| 3 || May 20th || A-2 ||<#CCFFCC> || ||
|| 4 || May 27th || A-2 ||<#CCFFCC> || ||
Line 19: Line 18:
|| 5 || June 3rd || ||<#CCFFCC> ||Alpha 1 ||
|| 6 || June 10th || ||<#CCFFCC> || ||
|| 7 || June 17th || ||<#CCFFCC> /!\ FeatureDefinitionFreeze || ||
|| 8 || June 24th || ||<#CCFFCC> /!\ DebianImportFreeze || ||
|| 5 || June 3rd || A-2 ||<#CCFFCC> ||Alpha 1 ||
|| 6 || June 10th || A-2 ||<#CCFFCC> || ||
|| 7 || June 17th || A-2 ||<#CCFFCC> /!\ FeatureDefinitionFreeze || ||
|| 8 || June 24th || A-2 ||<#CCFFCC> /!\ DebianImportFreeze || ||
Line 24: Line 23:
|| 9 || July 1st ||   ||<#FFFFCC> || Alpha 2 ||
|| 10 || July 8th || ||<#FFFFCC> || ||
|| 11 || July 15th || ||<#FFFFCC> || ||
|| 12 || July 22nd || ||<#FFFFCC> || ||
|| 13 || July 29th || ||<#FFFFCC> || Ubuntu 10.04.1 ||
|| 9 || July 1st || Iteration Planning ||<#FFFFCC> || Alpha 2 ||
|| 10 || July 8th || A-3 ||<#FFFFCC> || ||
|| 11 || July 15th || A-3 ||<#FFFFCC> || ||
|| 12 || July 22nd || A-3 ||<#FFFFCC> || ||
|| 13 || July 29th || A-3 ||<#FFFFCC> || Ubuntu 10.04.1 ||
Line 30: Line 29:
|| 14 || August 5th || ||<#FFEBBB> || Alpha 3 ||
|| 15 || August 12th || ||<#FFEBBB> /!\ PartnerUploadDeadline || ||
|| 16 || August 19th || ||<#FFEBBB> || ||
|| 17 || August 26th || ||<#FFEBBB> /!\ FeatureFreeze || ||
|| 14 || August 5th || Iteration Planning ||<#FFEBBB> || Alpha 3 ||
|| 15 || August 12th || A-4 ||<#FFEBBB> /!\ PartnerUploadDeadline || ||
|| 16 || August 19th || A-4 ||<#FFEBBB> || ||
|| 17 || August 26th || A-4 ||<#FFEBBB> /!\ FeatureFreeze || ||
Line 35: Line 34:
|| 18 || September 2nd || ||<#FFCCCC> || Alpha 4 ||
|| 19 || September 9th || ||<#FFCCCC> || ||
|| 20 || September 16th || ||<#FFCCCC> /!\ UserInterfaceFreeze|| ||
|| 21 || September 23th || ||<#E47A7A> || Beta ||
|| 22 || September 30th || ||<#E47A7A> /!\ DocumentationStringFreeze || ||
|| 18 || September 2nd || Iteration Planning ||<#FFCCCC> || Alpha 4 ||
|| 19 || September 9th || Beta UI ||<#FFCCCC> || ||
|| 20 || September 16th || Beta UI ||<#FFCCCC> /!\ UserInterfaceFreeze|| ||
|| 21 || September 23th || Quality ||<#E47A7A> || Beta ||
|| 22 || September 30th || Quality ||<#E47A7A> /!\ DocumentationStringFreeze || ||
Line 41: Line 40:
|| 23 || October 7th || ||<#E47A7A> || ||
|| 24 || October 14th || ||<#E47A7A> /!\ FinalFreeze, /!\ KernelFreeze, /!\ NonLanguagePackTranslationDeadline || ||
|| 25 || October 21st || ||<#E47A7A> /!\ ReleaseCandidate, /!\ LanguagePackTranslationDeadline || ReleaseCandidate ||
|| 26 || October 28th || ||<#E47A7A> /!\ '''FinalRelease''' || {*} '''Ubuntu 10.10''' ||
|| 23 || October 7th || Quality ||<#E47A7A> || ||
|| 24 || October 14th || Quality ||<#E47A7A> /!\ FinalFreeze, /!\ KernelFreeze, /!\ NonLanguagePackTranslationDeadline || ||
|| 25 || October 21st || Quality ||<#E47A7A> /!\ ReleaseCandidate, /!\ LanguagePackTranslationDeadline || ReleaseCandidate ||
|| 26 || October 28th || Quality ||<#E47A7A> /!\ '''FinalRelease''' || {*} '''Ubuntu 10.10''' ||
Line 46: Line 45:
== Work Item Iterations ==
<<Include(/WorkItemIterations)>>
  • Please do not edit

  • Freezes normally happen at the start of the given date, UTC time. So last minute changes need to happen the day before.
  • Some background information and Q&A about the Ubuntu release process can be found on TimeBasedReleases

  • See the Schedules of other projects

Google calendar of Maverick Meerkat schedule
Maverick Meerkat schedule as iCal

Week

Date (Thursday)

Work Item Iteration

Status

Notes

May 2010

1

May 6th

A-2

Info <!> Toolchain Uploaded

2

May 13th

A-2

Ubuntu Developer Summit

3

May 20th

A-2

4

May 27th

A-2

June 2010

5

June 3rd

A-2

Alpha 1

6

June 10th

A-2

7

June 17th

A-2

Warning /!\ FeatureDefinitionFreeze

8

June 24th

A-2

Warning /!\ DebianImportFreeze

July 2010

9

July 1st

Iteration Planning

Alpha 2

10

July 8th

A-3

11

July 15th

A-3

12

July 22nd

A-3

13

July 29th

A-3

Ubuntu 10.04.1

August 2010

14

August 5th

Iteration Planning

Alpha 3

15

August 12th

A-4

Warning /!\ PartnerUploadDeadline

16

August 19th

A-4

17

August 26th

A-4

Warning /!\ FeatureFreeze

September 2010

18

September 2nd

Iteration Planning

Alpha 4

19

September 9th

Beta UI

20

September 16th

Beta UI

Warning /!\ UserInterfaceFreeze

21

September 23th

Quality

Beta

22

September 30th

Quality

Warning /!\ DocumentationStringFreeze

October 2010

23

October 7th

Quality

24

October 14th

Quality

Warning /!\ FinalFreeze, Warning /!\ KernelFreeze, Warning /!\ NonLanguagePackTranslationDeadline

25

October 21st

Quality

Warning /!\ ReleaseCandidate, Warning /!\ LanguagePackTranslationDeadline

ReleaseCandidate

26

October 28th

Quality

Warning /!\ FinalRelease

Ubuntu Ubuntu 10.10