MilestoneProcess

Differences between revisions 36 and 42 (spanning 6 versions)
Revision 36 as of 2011-02-09 18:19:52
Size: 5338
Editor: 99-191-111-134
Comment:
Revision 42 as of 2011-07-05 19:38:54
Size: 5856
Editor: 99-191-111-134
Comment: update to clarify what is actually happening with the technical overview page and web team
Deletions are marked like this. Additions are marked like this.
Line 9: Line 9:
 1. Ask the marketing team (ubuntu-marketing@lists.ubuntu.com) to prepare a web page about the changes since the last milestone
  * Please notify web team (email: richard.lee@canonical.com, IRC: rhlee) that there will be impending website changes
  * Review list of full iso image names and sizing with Richard Lee
 1. Start to prepare web page summarizing the changes since the last milestone
  * Set up template
  *
Ask the marketing team (ubuntu-marketing@lists.ubuntu.com) if they have input
  * Notify the technical leads and product managers/designates for their input.
 1. Coordinate with web team for contacts and plans during release day
  *
Please notify web team (email: ellen.arnold@canonical.com, IRC:ellen) that there will be impending website changes
  * Review list of full iso image names and sizing with the web team (ellen.arnold@canonical.com, IRC ellen)
Line 23: Line 27:
 1. Announce the milestone freeze on the `#ubuntu-devel` topic, [[http://lists.ubuntu.com/mailman/listinfo/ubuntu-devel-announce|ubuntu-devel-announce]], and [[https://release-blog.ubuntu.com/wp-admin/edit.php|http://release-blog.ubuntu.com/]]. There is generally no need to tell people to hold off on uploads, as they will be held automatically by Soyuz once the next task is performed.  1. Announce the milestone freeze on the `#ubuntu-devel` topic, [[http://lists.ubuntu.com/mailman/listinfo/ubuntu-devel-announce|ubuntu-devel-announce]]. If it is not a hard freeze, let people know to hold off on the uploads. When it is a hard freeze, they will be held automatically by Soyuz once the next task is performed.
Line 25: Line 29:
 1. As first image becomes available, mail out to ubuntu-devel@lists.ubuntu.com and ubuntu-bugsquad@lists.ubuntu.com to announce that ISO images are ready for testing, and refer people to the ISO tracker.
Line 28: Line 33:
  * [[http://people.ubuntu.com/~ubuntu-archive/NBS|NBS]] list   * [[http://people.ubuntu.com/~ubuntu-archive/nbs.html|NBS]] list
Line 30: Line 35:
 1. Ensure that you accept at least one package through the [[https://launchpad.net/ubuntu/natty/+queue?batch=300&queue_state=1|Launchpad UI]], to ensure that launchpad has not broken (important for non-Canonical members of the release team). If it has, please file a bug on [[https://bugs.launchpad.net/soyuz/+bugs|Soyuz]], and scream loudly.  1. Ensure that you accept at least one package through the [[https://launchpad.net/ubuntu/oneiric/+queue?batch=300&queue_state=1|Launchpad UI]], to ensure that launchpad has not broken (important for non-Canonical members of the release team). If it has, please file a bug on [[https://bugs.launchpad.net/soyuz/+bugs|Soyuz]], and scream loudly.
Line 39: Line 44:
 1. Prepare the release web page content (technical overview)
   * review input from tech leads
   * add discovered bugs not going to be fixed from ISO testing
   * Review `-changes` mailing list since the last milestone to make sure that all relevant major changes have been documented in the milestone's web page
Line 40: Line 49:
  * Review `-changes` mailing list since the last milestone to make sure that all relevant major changes have been documented in the milestone's web page
* this should refer to the web page prepared by the marketing team rather than going into details of changes itself
  * update the page to include any caveats
   * this should refer to the summary web page prepared by the teams rather than going into details of changes itself
   * update the page to include any caveats
Line 52: Line 60:
 1. Notify web site team (e: Richard.Lee@canonical.com, IRC: rhlee) to update to new images and notes.  1. Notify web site team (email:  ellen.arnold@canonical.com, IRC: ellen) to update to new images and notes.
Line 73: Line 81:
 * Warn the QA team (ubuntu-bugsquad@lists.ubuntu.com)

To be carried out by: Ubuntu Release Manager, with support from the Ubuntu release team

Goals:

  • Produce a set of distribution media images suitable for testing by advanced users and hardware recertification
  • Make the archive consistent so that upgrade testing can be performed

Release minus 6 days:

  1. Start to prepare web page summarizing the changes since the last milestone
    • Set up template
    • Ask the marketing team (ubuntu-marketing@lists.ubuntu.com) if they have input

    • Notify the technical leads and product managers/designates for their input.
  2. Coordinate with web team for contacts and plans during release day
  3. Notify developers by mailing ubuntu-devel-announce:

    • Pointer to milestone release notes page
    • Reminder of milestone freeze
    • Request to avoid and eliminate PackageInconsistencies

    • Target any relevant bugs to the milestone
  4. Merge seeds and update metapackages for all releasing derivatives
  5. Notify Michael Vogt to perform a GnomeAppInstallDesktopDatabaseUpdate

  6. Discuss with Desktop team and MartinPitt whether or not to re-enable apport by default.

Release minus 2 days:

  1. Announce the milestone freeze on the #ubuntu-devel topic, ubuntu-devel-announce. If it is not a hard freeze, let people know to hold off on the uploads. When it is a hard freeze, they will be held automatically by Soyuz once the next task is performed.

  2. If a hard freeze is in use, set the distrorelease status to FROZEN in Launchpad

  3. As first image becomes available, mail out to ubuntu-devel@lists.ubuntu.com and ubuntu-bugsquad@lists.ubuntu.com to announce that ISO images are ready for testing, and refer people to the ISO tracker.

  4. Review problems and file targeted bugs for those which need resolution before builds can begin:
  5. Selectively accept package uploads to resolve targeted bugs
  6. Ensure that you accept at least one package through the Launchpad UI, to ensure that launchpad has not broken (important for non-Canonical members of the release team). If it has, please file a bug on Soyuz, and scream loudly.

Release minus 1 day:

  1. Resolve any remaining targeted bugs
  2. Begin UpgradeTestingProcess, since the archive is now consistent

  3. Stop all live filesystem and cdimage cron jobs
  4. Produce full set of images
  5. Iterate ReleaseValidationProcess and fix showstopper bugs

  6. Prepare the release web page content (technical overview)
    • review input from tech leads
    • add discovered bugs not going to be fixed from ISO testing
    • Review -changes mailing list since the last milestone to make sure that all relevant major changes have been documented in the milestone's web page

  7. Prepare the release announcement
    • this should refer to the summary web page prepared by the teams rather than going into details of changes itself
    • update the page to include any caveats

Release:

  1. If there is a previous milestone for this series, move those images from /srv/cdimage.ubuntu.com/www/full to /srv/cdimage.ubuntu.com/old-images/, and notify the sysadmin team that these are available for off-line archival.
  2. Publish the milestone CD images: ./publish-image-set.py (from lp:ubuntu-archive-tools) will print the necessary commands.

  3. Publish the milestone UEC images on uec-images.ubuntu.com.

  4. Notify Hardware Certification team ( email: Ara.Pulido@canonical.com, IRC: ara ) to begin CertificationTestingProcess (private due to agreements with vendors)

  5. Verify that all mirrors listed in the announcement or release notes have images
  6. Check functionality of torrents
  7. Notify web site team (email: ellen.arnold@canonical.com, IRC: ellen) to update to new images and notes.

    • /testing on the website with release notes

    • alphas are served off of cdimage, betas and others use `/testing/download
  8. Send the release announcement to ubuntu-devel-announce

  9. Confirm that UpgradeTestingProcess is complete before unfreezing archive

  10. If a hard freeze was in use, set the distrorelease back to DEVELOPMENT in Launchpad

  11. Update the topic on #ubuntu-devel

  12. Post an announcement on http://release-blog.ubuntu.com/

  13. Clear out any pending entries in the UNAPPROVED queue

  14. Turn live filesystems and cdimage cron jobs back on.
  15. Release manager to mark the old milestone inactive in Launchpad (https://launchpad.net/ubuntu/RELEASE)

  16. Release manager to work through any old milestoned bugs still remaining, and move to next milestone if appropriate.
  17. Release manager update the burndown chart links on ReleaseTeam/FeatureStatus

  18. If any modifications to this process were made in this run, check whether they apply to BetaProcess and ReleaseProcess as well.

Release plus 7 days:

  1. In planning cycle, review Release Manifest and make any necessary updates.

Outstanding issues


CategoryProcess