WorkItemIterations

Work Item Iteration

Work Milestone

Start Date

End Date

Notes/Events

Planning

Release Planning, Alpha 1 Work Items, Alpha 2 planning

October 11th

November 26th

Feature Definition Freeze (11/26)

1

Alpha 2 Work Items

November 1st

January 27th

Alpha 1 (12/2) Debian Import Freeze (12/30)

Alpha 2 bug fixing, Alpha 3 planning

January 28th

February 3rd

Alpha 2 (2/3)

2

Alpha 3 Work Items

February 3rd

February 24th

10.04.2 (2/17), Feature Freeze (2/24)

Alpha 3 Bug Fixing, Beta planning

February 25th

March 3rd

Alpha 3 (3/3)

3

Beta UI completion work, Beta Bug Fixing, Beta Release

March 3rd

March 31st

UI Freeze (3/24), Beta (3/31)

Quality

Bug Fixing, Release Candidate Work Items

April 1st

April 14th

Kernel Freeze (4/??), Final Freeze (4/14), Non Language Pack Translation Deadlines(4/14)

Release Critical bug fixing, Release Work Items

April 14st

April 28th

Release Candidate (4/??), Language Pack Translation Deadline (4/??), Final Release (4/28)


NattyReleaseSchedule/WorkItemIterations (last edited 2010-11-24 21:28:09 by 99-191-111-134)