WorkItemIterations
Work Item Iteration |
Work Milestone |
Start Date |
End Date |
Notes/Events |
Planning |
Release Planning, Alpha 1 Work Items, Alpha 2 planning |
October 11th |
November 26th |
Feature Definition Freeze (11/26) |
1 |
Alpha 2 Work Items |
November 1st |
January 27th |
Alpha 1 (12/2) Debian Import Freeze (12/30) |
|
Alpha 2 bug fixing, Alpha 3 planning |
January 28th |
February 3rd |
Alpha 2 (2/3) |
2 |
Alpha 3 Work Items |
February 3rd |
February 24th |
10.04.2 (2/17), Feature Freeze (2/24) |
|
Alpha 3 Bug Fixing, Beta planning |
February 25th |
March 3rd |
Alpha 3 (3/3) |
3 |
Beta UI completion work, Beta Bug Fixing, Beta Release |
March 3rd |
March 31st |
UI Freeze (3/24), Beta (3/31) |
Quality |
Bug Fixing, Release Candidate Work Items |
April 1st |
April 14th |
Kernel Freeze (4/??), Final Freeze (4/14), Non Language Pack Translation Deadlines(4/14) |
|
Release Critical bug fixing, Release Work Items |
April 14st |
April 28th |
Release Candidate (4/??), Language Pack Translation Deadline (4/??), Final Release (4/28) |
NattyReleaseSchedule/WorkItemIterations (last edited 2010-11-24 21:28:09 by 99-191-111-134)