- Freezes normally happen around 2100 UTC time of the given date. This permits those last changes to be incorporated into the nightly builds. Last minute changes need to happen before then unless otherwise indicated by the release team.
The release engineer for any given milestone can be found at the Release Task Signup page.
Some background information and Q&A about the Ubuntu release process can be found on TimeBasedReleases
See the Schedules of other projects
Week |
Date (Thursday) |
15.04 Events |
||
October 2014 |
||||
1 |
October 30th |
Toolchain Uploaded |
||
November 2014 |
||||
2 |
November 6th |
|
||
3 |
November 13th |
vUDS (Wednesday - Friday) |
||
4 |
November 20th |
|
||
5 |
November 27th |
|||
December 2014 |
||||
6 |
December 4th |
|
||
7 |
December 11th |
|
||
8 |
December 18th |
Alpha 1 (for opt-in flavors) |
||
9 |
December 25th |
|
||
January 2015 |
||||
10 |
January 1st |
|
||
11 |
January 8th |
|
||
12 |
January 15th |
|
||
13 |
January 22nd |
Alpha 2 (for opt-in flavors) |
||
14 |
January 29th |
|
||
February 2015 |
||||
15 |
February 5th |
|
||
16 |
February 12th |
|
||
17 |
February 19th |
|||
18 |
February 26th |
Beta 1 Freeze (Monday), Beta 1 (for opt-in flavors) |
||
March 2015 |
||||
19 |
March 5th |
|
||
20 |
March 12th |
|||
21 |
March 19th |
|||
22 |
March 26th |
Final Beta Freeze, Final Beta |
||
April 2015 |
||||
23 |
April 2nd |
|
||
24 |
April 9th |
|||
25 |
April 16th |
FinalFreeze, ReleaseCandidate, LanguagePackTranslationDeadline |
||
26 |
April 23rd |
FinalRelease Ubuntu 15.04 |